Metropolitan Branch Trail – Summer ’09?

As we near the Vernal Equinox, physical work on the Metropolitan Branch Trail has yet to commence.  However, DDOT has recently suggested a late-March early-April groundbreaking.mbt

The contractor, Fort Myer, was selected for the design-build contract.  Although some aspects of the trail were stipulated by DDOT, the firm was tasked with developing much of the design plan–which we assume is close to, if not, finalized.

The contract was signed on July 22, 2008 and, as written in the contract, the work must be completed in 12 months. DDOT has confirmed that no extention has been granted.

So, while our earlier hopes of a spring opening have been dashed, those who have watched this Trail face nearly 15 years of delays should feel fairly confident of a summer opening.

Advertisements

3 thoughts on “Metropolitan Branch Trail – Summer ’09?

  1. I really hope this is completed by the Summer. I’ve lived in the neighborhood for three long years and I’ve been waiting for this project to be completed. It seems like this project should be a no-brainer. I can’t wait to have a decent bike path nearby that will connect me to everything that NOMA promises to eventually be.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s