Metropolitan Branch Trail – Summer ‘09?

2009 March 16
by flatland

As we near the Vernal Equinox, physical work on the Metropolitan Branch Trail has yet to commence.  However, DDOT has recently suggested a late-March early-April groundbreaking.mbt

The contractor, Fort Myer, was selected for the design-build contract.  Although some aspects of the trail were stipulated by DDOT, the firm was tasked with developing much of the design plan–which we assume is close to, if not, finalized.

The contract was signed on July 22, 2008 and, as written in the contract, the work must be completed in 12 months. DDOT has confirmed that no extention has been granted.

So, while our earlier hopes of a spring opening have been dashed, those who have watched this Trail face nearly 15 years of delays should feel fairly confident of a summer opening.

3 Responses leave one →
  1. 2009 March 18
    Anonymous permalink

    I really hope this is completed by the Summer. I’ve lived in the neighborhood for three long years and I’ve been waiting for this project to be completed. It seems like this project should be a no-brainer. I can’t wait to have a decent bike path nearby that will connect me to everything that NOMA promises to eventually be.

  2. 2009 April 29
    Anonymous permalink

    This shizznizz ain’t happen’n.

Trackbacks & Pingbacks

  1. State of the ‘hood Address « eckington (way better than spotsylvania)

Leave a Reply

Note: You can use basic XHTML in your comments. Your email address will never be published.

Subscribe to this comment feed via RSS